Also, operational safety and working conditions will be improved. To these ends, an edger of the hot strip mill will be upgraded, short stroke HAGC (hydraulic gap control cylinders) will be installed in the finishing mill, and the cooling line will be outfitted with a Power Colling unit. The latter allows for an alloy-saving production of high-end steel grades. In addition, a Primetals level 2 control model consisting of physical process models with advanced optimization strategies and neural network algorithms for adaptation will be installed.
Severstal Russian Steel Division is a part of PAO Severstal, a vertically integrated steel and steel-related mining company with major assets in Russia as well as investments in other regions. Steel production volume of PAO Severstal in 2017 was around 11.65 million metric t of liquid steel. The steel is used to make a large number of end products, including hot- and cold-rolled flat steel, galvanized and coated products, and long products. At the “HSM 2000”, Primetals will install new mechanic, hydraulic and electric equipment and implement the corresponding automation solutions and process models.
To improve strip thickness control in addition to the existing mechanical screw down system, short stroke hydraulic gap setting cylinders will be implemented in the first three stands (F6 to F8) of the finishing mill.
The technological key functions will be replaced with the latest state of the art control algorithms. The existing level 2 system will be upgraded to extend lifetime and include present technological models. Profile and flatness control models will be added as new functions.
The cooling section will be controlled by a new automation system, ensuring the correct cooling strategy and cooling path as defined by the coiling temperature and the cooling rate is followed. Strip temperature tracking already starts at the roughing mill exit. A Comprehensive Temperature Control will be supplied for coordinated control of finishing mill speed, inter-stand cooling and coiling temperature. The cooling section control includes intelligent water management to cope with the highly dynamic requirements of large water flow rates. The run-out roller table downstream from the finishing mill conveys the strip through the laminar cooling line to the down coiler groups 1 and 2. In cooling section 1, right after the finishing mill, a new Power Cooling system will be installed. Also, the laminar cooling headers in this section will be renewed. In section 2, only the trimming headers will be replaced.
(Source: Primetals Technologies, Limited)
Primetals Technologies receives order from Jeevaka Industries for new billet caster and high-speed rebar outlet
Indian steel producer Jeevaka Industries Private Limited has commissioned Primetals Technologies to implement a three-strand billet caster and a high-speed rebar outlet at its new steel mill in Hyderabad, Telangana.