Blast furnace 2 has a hearth diameter of 12 m and an inner volume of approximately 3,300 m3. Average production is 6,900 metric t per day. The third rebuild of blast furnace 2 includes a complete shell and cooling system replacement. The cooling system will be a combination of copper and cast-iron staves from hearth to upper stack. Primetals was contracted to supply nine rows of cast-iron staves. The installation of the new staves is scheduled to take place during a planned shutdown period in 2020. Blow-in of the rebuilt furnace is expected for early 2021.
CSC is the leading steel producer in Taiwan with an annual production of around 10 million metric t per year. Around two thirds of the production is for the domestic Taiwanese market, the rest is exported. CSC produces a range of products including plates, bars, wire rods, hot and cold rolled coils, electrogalvanised coils, electrical steel coils, hot-dip galvanised coils, and Ti/Ni-base alloy.
The CSC plant in Kaohsiung includes two BOF shops with a total of seven 2-strand slab casters and three 4-strand bloom casters. The slab casters mainly produce carbon and low alloy steels. In addition to supplying BF equipment, Primetals recently upgraded a continuous slab caster at CSC´s Kaohsiung plant.
(Source: Primetals Technologies, Limited)
SEW-EURODRIVE verlegt Standort des Drive Technology Center West
Nach rund zwei Jahren Bauzeit war es so weit: Das Drive Technology Center (DTC) West des Antriebs- und Automatisierungsspezialisten SEW-EURODRIVE ist am 1. Juli 2025 vom Standort Langenfeld in ein neues Gebäude im Technologiepark Haan-Gruiten umgezogen.