In 1982, the No. 1 RH facility (160 t) had been commissioned by a company which today is part of SMS group and, in 1990, SMS Mevac had modernised it in a record time of only 73 days. CSC uses the facility for hydrogen degassing in the production of high-grade heavy plate.
SMS group’s supply scope includes the design of the layout, the engineering, manufacturing and supply of the equipment, and commissioning, which will take place in 2020.
Thanks to the increased extraction capacity of the new pump to 600 kg/h at 0.67 mbar, it is easier to compensate system leakages and evacuation times will be shorter. Additionally, the new vacuum pump can be operated at condenser cooling-water temperatures of up to 38 °C, boosting the flexibility of the RH unit, especially during the hot summer months.
(Source: SMS group)
GRT comes to Europe and brings new momentum to industrial parts cleaning
The European market for industrial parts cleaning is considered demanding—dense, established, and difficult to enter.