Generic filters
FS Logoi
Generic filters

Work to complete the new continuous casting system S1 is on schedule

Since the middle of November 2017, construction work on the new continuous casting system S1 in the steel plant of Saarstahl has been running at full speed. The project represents a total investment of € 100 mil. and requires that all tasks be coordinated with the greatest precision to ensure that the system can go into operation according to schedule at the end of 2019.

von | 20.02.19

picture: © Dirk Martin/Saarstahl AG

The new S1 is a five-strand circular arc system followed by a comprehensive soft reduction zone. In this zone, the strand in the semi-solid state is defined using upper and lower rolls thus improving the internal microstructure of the steel decisively.
Martin Baues, Chief Technical Officer at Saarstahl, gave representatives of the media a rare look behind the scenes at the ongoing construction work: “This construction site is particularly challenging for us since the new continuous casting plant is the first system in the world designed with mechanical soft reduction (MSR) for casting formats of 180 mm x 180 mm and which is also equipped with the latest automation and communication technology. We are glad and proud that we are precisely on schedule with the construction work.”
The system will be erected in the location where the “old” S1 was decommissioned in 2010. After the dismantling work on the old system and work to build the functional building and in the area of the system pit, now assembly of the main components is being carried out i. e. the continuous casting machine itself and the turnover cooling bed as well as assembly of auxiliary aggregates and the infrastructure. To date, around 125 partner companies have worked on the construction site. Of these, around 70 % are based in the Saarland and in the surrounding area. At the same time, a maximum of around 200 people are working on the construction site at any one time and, in total, 800 people will have been involved in the completion of the project.
Martin Baues highlighted the concept and significance of the system saying, “We are equipping the new continuous casting system S1 with the latest automation and communication technology and we already took the approach of industry 4.0 into account in developing the concept. This will enable us to monitor the processes on the new system even better and to ensure a maximum in quality assurance. As a result, we will be able to manufacture steel solutions tailored to our customers individual requirements even more flexibly and faster in the future.”
(Source: SHS – Stahl-Holding-Saar GmbH &co. KG)

Bildquelle, falls nicht im Bild oben angegeben:

Jetzt Newsletter abonnieren

Die ganze Welt der Metallurgie, immer in Ihrem Postfach.

Hier anmelden

Aktuelles Seminar: „Elektrothermische Prozesstechnik“

Aktuelles Seminar: „Elektrothermische Prozesstechnik“

Das Institut für Elektroprozesstechnik der Leibniz Universität Hannover (ETP) veranstaltet in Zusammenarbeit mit der Forschungsvereinigung Industrieofenbau e.V. (FOGI) am 24. und 25. Februar 2026 in Hannover das aktuelle Seminar „Elektrothermische Prozesstechnik“.

mehr lesen
GMH Gruppe verlängert Vorstandsverträge bis 2030

GMH Gruppe verlängert Vorstandsverträge bis 2030

Der Aufsichtsrat der GMH Gruppe hat die Verträge der Vorstandsmitglieder Dr. Alexander Becker (Chief Executive Officer), Dr. Anne-Marie Großmann (Chief Development Officer) und Mathias Hölscher (Chief Financial Officer) bis 2030 verlängert.

mehr lesen

Fachinformationen für Sie